Item Coversheet
      

5919 MAIN STREET .  NEW PORT RICHEY, FL 34652 . 727.853.1016


TO:City of New Port Richey City Council
FROM:Robert M Rivera – Public Works Director
DATE:1/2/2024
RE:2024 Sims Park Playground Surface Replacement

REQUEST:

The action requested of City Council is to review and consider the approval of the attached proposal from Top Line Recreation Inc., in the amount not to exceed $119,152.83. The proposal contains pricing in accordance with the current Clay County Contract RFP No. 18/19-2.



DISCUSSION
:

As the City Council is aware, improvements to Sims Park were completed in 2016. Included in the improvements was the relocation and expansion of the existing playground.  Existing playground equipment was replaced with modern equipment containing up to date safety features.  Finally, the existing playground surface containing wood chips was replaced with a Poured-in-Place (PIP) playground surfacing.  The typical life span for this type of surfacing is seven to ten years depending on usage.  The existing surface is eight years old and contains several major repairs and is in need of replacement due to safety concerns and maintenance costs.     



RECOMMENDATION:

Approval of the attached proposal is recommended.



BUDGET/FISCAL IMPACT:

This project is included in the City’s 2023-2024 Capital Improvement Program account number 301301.46326.

ATTACHMENTS:
DescriptionType
Piggybacking Check ListBackup Material
ProposalBackup Material
Terms and ConditionsBackup Material
Product BrochureBackup Material