Item Coversheet
      

5919 MAIN STREET .  NEW PORT RICHEY, FL 34652 . 727.853.1016


TO:City of New Port Richey City Council
FROM:Robert M. Rivera, Public Works Director
DATE:2/20/2024
RE:2023 RAC Activity Pool Resurfacing Project Close Out

REQUEST:

The request before City Council is to review and consider for approval the attached deductive change order in the amount of ($10,271.34) and the final pay request in the amount not to exceed $97,166.16 Submitted by AuMiller Pools, LLC for the completion of the 2023 RAC Activity Pool Resurfacing Project.



DISCUSSION
:

The scope of this project included the resurfacing of the Activity Pool at the Recreation and Aquatics Center. Typically pool resurfacing occurs eight to 12 years from the previous application.  The original pool surface was constructed 15 years ago.   The existing surface had become coarse over time and was in need of replacement. In addition, a number of items were included as part of the project.  These included:

1.     Replacement of existing tiles.

2.     Replacement of existing inlet grates.

3.     Replacement of existing outlet covers.

4.     Rehabilitation of the existing fish slide.

5.     Rehabilitation of the existing mushroom feature.



RECOMMENDATION:

Approval of the deductive change order and final pay request is recommended.



BUDGET/FISCAL IMPACT:

The funding to support this project has been budgeted in the City's FY 2023-2024 Capital Improvement Program.

ATTACHMENTS:
DescriptionType
Final Pay RequestBackup Material
Deductive Change OrderBackup Material
PhotosBackup Material