Item Coversheet
      

5919 MAIN STREET .  NEW PORT RICHEY, FL 34652 . 727.853.1016


TO:City of New Port Richey City Council
FROM:Robert M Rivera, Public Works Director
DATE:8/6/2019
RE:Orange Lake Improvements Project Close Out

REQUEST:

The request from staff for City Council is to review and consider for approval the attached deductive change order in the amount of ($24,517.86) and the final pay request in the amount of $237,976.55 from Augustine Construction, Inc., for the Orange Lake Restoration and Improvements Project ITB18-003.



DISCUSSION
:

As City Council is aware, historically Orange Lake has discharged stormwater into the river with minimal treatment.  In an effort to satisfy the water quality element of the City's National Pollution Discharge Elimination System (NPDES) permit, Federal and State grant agreements, the dredging and removal of sediments was completed by the City in March of 2018.  Due to the special nature of dredging, it was the recommendation of the design engineer to City staff, the dredging of the lake be performed as a stand-alone project or phase 1 of the restoration and improvements to the lake.

 

Several other water quality elements were proposed and included in the Orange Lake Restoration and Improvements Project.  They included, the installation of  several pollution control boxes, the installation of a diffusion system, littoral zone creations, slide gates for flood control, and installation of boardwalks on the west and east sides of the lake as part of the outreach portion overlooking the littoral zone creations.  These project elements where considered as phase 2 and completed as part of this project.



RECOMMENDATION:

Approval of the deductive change order and final pay request is recommended.



BUDGET/FISCAL IMPACT:

Funding for the project is identified as Capital Improvement Dollars.  

ATTACHMENTS:
DescriptionType
Deductive Change OrderBackup Material
Final Pay RequestBackup Material