| TO: | City of New Port Richey City Council | | FROM: | Robert M. Rivera, Public Works Director | | DATE: | 7/20/2021 | | RE: | 2020 NPR Pasco Potable Water Interconnect Upgrades Project – Engineering Services |
REQUEST:
The request of staff for City Council is to review and consider the attached task order in the not to exceed amount of $52,500 from Stroud Engineering Consultants, Inc. for the 2021 NPR Pasco Potable Water Interconnect Upgrades.
DISCUSSION: The scope of deliverables in the attached engineering task order include design phase services, permit assistance, bid, and construction services. Design and construction elements of the project include sub-underground engineering (SUE) work within the roadway, maintenance of traffic, valve removal, valve installations, a temporary bypass assembly, and demolishing the existing interconnect. The replacement of the existing standard potable bulk meter with a smart bulk meter and the installation of a pressure sustaining valve. This project is part of several phases to upgrade to the City’s interconnections. These interconnects contain antiquated meter technology as well as valve and bypass systems that have served their useful life and are no longer dependable.
RECOMMENDATION:
Approval of the task order is recommended.
BUDGET/FISCAL IMPACT:
Funding for this project is made available in the Water and Sewer Capital Construction Program line item #405533-46391-0952 | | | |