Item Coversheet

5919 MAIN STREET .  NEW PORT RICHEY, FL 34652 . 727.853.1016


TO:Members of the Community Redevelopment Agency
FROM:Barbara Carr, Economic Development Director
DATE:9/26/2022
RE:Request for Extension on Performance Agreement for Central Orange Partners, LLC - Page 11

REQUEST:

The Performance Agreement between Central Orange Partners, LLC, and the Community Redevelopment Agency dated January 21, 2019 has been impacted by Covid-19 pandemic and subsequent disruptions to the construction industry.  This has resulted in a change to the timeframe outlined in the agreement for Phase II and III. 




DISCUSSION:

Update to the Phase II and III timeline for commencement and completion of the construction is being requested by Central Orange Partners, LLC.

 

The Performance Agreement dated January 21, 2019 in Section 8 states, "Extensions.  Unless otherwise provided herein, in the event Developer encounters unforeseen conditions sufficient to warrant an extension of time for the Commencement and Completion Periods provided herein, it may request such an extension from City, which may be granted or denied within City's discretion, which shall not be unreasonably withheld. " This Section 8 of the agreement allows the commencement of and the construction with minor revisions if warranted. 

 

Phase I has been completed and has been fully leased since January 2021.  

 

The requested change is that Phase II would begin commencement no later than December 31, 2022 with construction completed by December 31, 2024. This extension would provide an additional 11 months to the agreement approved by the Community Redevelopment Agency in November of 2021. 




RECOMMENDATION:

Staff recommends the commencement of Phase II and III be extended from January 21, 2022 and changed to December 31, 2022

(Additional 11 months to the timeframe)

 

Staff recommends the construction of Phase II and III be extended from January 21, 2024 and allowed to be changed to December 31, 2024. 

(Additional 11 months to the timeframe)




BUDGET / FISCAL IMPACT:
Exhibit "B" in the agreement allowed for Property Tax Rebates.  The expectation was construction would be completed by 2020 and as a result the TIF incentive will be less for the project after the completion of the construction.
ATTACHMENTS:
DescriptionType
Extension Request LetterBackup Material
Executed Performance Agreement dated January 21, 2019Exhibit